NRW can start early work at Bullabulling. The A$1 billion contract still awaits a decision

The contractor expects to use mostly existing equipment at first. Minerals 260 still needs to approve the project and close on previously announced financing.

Sources

Sources & evidence

What “Source checked” means

NRW Holdings has been picked to prepare for mining at the Bullabulling gold project in Western Australia. The contractor can begin early work now, but the full agreement, which NRW estimates at about A$1 billion over its first five years, is expected to be signed alongside Minerals 260’s final investment decision in early 2027. That distinction matters for both companies. NRW has a preferred position, not five years of contracted revenue. Minerals 260 can advance preparations, but has not announced a decision to build the mine.

Early work is not the start of mining

The early-services letter allows NRW to get ready to deploy people and equipment. The company expects to mobilise fully in the third quarter of 2027, start mining in the fourth quarter and support Minerals 260’s target of first gold production in 2028.

The planned scope includes preparing the site, removing material above the ore, managing water, and loading and hauling material. NRW’s Action Drill & Blast subsidiary would handle drilling and blasting.

The proposed contract runs for five years with an option to extend. NRW expects activity to build over the first three years, so the estimated value does not translate into a fixed annual revenue figure.

The first fleet would mostly come from existing equipment

NRW expects to supply most of the fleet from equipment it already owns that is idle. That puts existing equipment back to work rather than requiring the contractor to buy an entirely new fleet up front.

NRW still expects about A$20 million of new equipment investment in fiscal 2028 and about A$80 million more from the third contract year. Those figures describe NRW’s spending on its fleet, not Minerals 260’s construction budget or a deduction from the estimated contract value.

Nor does the A$1 billion estimate disclose how profitable the work will be for NRW. The contractor did not give a margin or a year-by-year revenue schedule in the announcement.

Financing and permits have separate steps

Earlier this month Minerals 260 said it had signed credit-approved commitments for A$410 million in debt facilities. That consists of a A$335 million project finance facility and an A$75 million working capital facility from ANZ, NAB and Société Générale.

The developer says those commitments, financing from a Franco-Nevada royalty and proceeds from its equity raising cover funding through first production. The bank commitments are not a drawdown. Financial close still requires definitive documents, completion of the feasibility study, final due diligence and an agreement governing the lenders’ and royalty holder’s rights.

Minerals 260 separately reported a works approval for facilities including the processing plant, power infrastructure and tailings storage. As of that notice, vegetation clearance and a mine development and closure proposal were still being assessed. The approval is one step in the process, not a blanket clearance for the mine.

The next milestone is the board decision

Minerals 260 was targeting the first quarter of 2027 for both the definitive feasibility study and its investment decision. The study is intended to firm up how the mine would be built and operated before the board commits to it.

A signed main contract would clarify the work secured by NRW. Until then, the clearest distinction is that early preparation can start while the long-term contract and mine development still depend on further decisions.

Sources & evidence

Source checked3 sources · 12 figures

Figure receipts

Every figure in this article, with the source it came from.

NRW Holdings Limited

November 26 Bullabulling early mining services letter

Exchange announcement · Nov 26, 2026

  • 1,000 Estimated mining contract value

    AUD millions · As of Proposed Bullabulling contract

  • 5 Initial mining contract term

    Years · As of Proposed Bullabulling contract

  • 3 Planned staged ramp-up period

    Years · As of Proposed Bullabulling contract

  • 20 Expected new fleet capital expenditure

    AUD millions · As of FY28

  • 80 Expected additional new fleet capital expenditure

    AUD millions · As of From year three of contract

  • Q3 2027 Target for full mobilisation

    Quarter · As of Calendar 2027

  • Q4 2027 Target for mining start

    Quarter · As of Calendar 2027

  • 2028 Target for first production

    Calendar year · As of Planned development

Minerals 260 Limited

November 11 Bullabulling debt commitments

Exchange announcement · Nov 11, 2026

  • 410 Credit-approved debt commitments

    AUD millions · As of November 11 financing commitments

  • 335 Project finance facility commitment

    AUD millions · As of November 11 financing commitments

  • 75 Working capital facility commitment

    AUD millions · As of November 11 financing commitments

  • Q1 2027 Target for feasibility study and final investment decision

    Quarter · As of Calendar 2027

Sources

Sources used for this piece.

  1. NRW Holdings Limited

    November 26 Bullabulling early mining services letter

    Exchange announcement · 2026-11-26

  2. Minerals 260 Limited · 2 documents

The full mining services agreement and investment decision are not yet announced. Earlier permit and financing statuses are attributed to their filing dates.

TickerGrove house illustration for trade coverage: a container ship loading beneath a crane

Get the Morning Brief — Weekday Morning Brief · Saturday Weekend Brief · Sunday Week Ahead

Discuss this story. Join TickerGrove on Discord to talk companies, earnings, and markets, or request future coverage.

Disclaimer

TickerGrove is education and journalism only. It is not investment advice, not a broker-dealer, and not a recommendation to buy, sell, or hold any security.

Nothing on this site is a pick or a return promise. Official economic prints and company filings are dated observations. External quote links open a separate service; TickerGrove does not host those prices.

Markets · All stories