Niron picked Alabama for its $1.8 billion magnet plant. The financing is still undisclosed.

Dothan won the site search for a factory targeting 10,000 metric tons a year. What Alabama has disclosed so far is public-site preparation, not how Niron will pay for the plant.

Sources

Sources & evidence

What “Source checked” means

Niron Magnetics chose Dothan, Alabama, for a planned $1.8 billion permanent-magnet factory on Friday, ending a site search it announced in March. The choice gives the project an address and a timetable: construction is expected to start in 2028 and production in 2029. Neither Niron nor Alabama’s governor disclosed how the plant itself would be financed.

What Friday’s announcement changed

Niron already put a figure of up to $1.8 billion on the project in March. It also described the same planned factory size and annual capacity. Friday’s announcement matters because it names where that project will go, rather than because it adds a second $1.8 billion investment or raises the earlier budget.

The company picked the 446-acre Westgate Super Site after considering locations in 22 states. The proposed campus would occupy 1.6 million square feet. Niron and the governor expect the project to create 700 jobs within five years. That is a projection, not a count of people already working at the site.

Dothan’s plant is designed for 10,000 metric tons a year, according to Reuters. That is the planned annual capacity, not Niron’s expected production in the first year. The company gave a target for starting production but did not say when it expects to reach full capacity.

Alabama helped get the site ready

Alabama’s October award identifies $3.5 million for site work and public infrastructure at Westgate. The recipient was the Industrial Development Board of the City of Dothan, not Niron.

Under the Growing Alabama program, taxpayers contribute to approved economic development organizations in exchange for a state tax credit. The state says private donations support improvements to publicly owned sites. Local partners also received state support in 2024 for land acquisition and development.

Those disclosures explain how Dothan made the site ready to compete. They don’t say what Niron will put up in equity, how much it intends to borrow or whether there will be additional project-specific incentives. The $3.5 million award is not a down payment from Alabama toward the company’s $1.8 billion budget.

Minnesota is the nearer test

Niron is already building its first full-scale plant in Sartell, Minnesota. The company held a steel-raising ceremony there in September and expects to open the plant in 2027. Reuters put the planned capacity at up to 1,500 metric tons annually, less than one-sixth of Dothan’s target.

Sartell also offers a contrast in what the company has said about financing. In August, Niron announced a loan of up to $150 million under a conditional federal commitment for construction and equipment in Sartell. A conditional commitment is not the same thing as cash drawn.

Later in August, Niron announced a separate $150 million loan from the Shakopee Mdewakanton Sioux Community for the same Minnesota plant. The company also reported an investment from Honda in September, at the Sartell steel-raising event, without disclosing its size in that announcement. The two loan announcements name Sartell, not Dothan.

A bigger plant comes after the first one

Permanent magnets are components in products such as motors and consumer electronics. Niron is trying to sell a version that does not use rare-earth elements. The relevant measure for buyers is not the number of sites announced. It is whether the plants can supply the volume buyers need on a timetable they can plan around.

Sartell’s opening is the earlier milestone. For Dothan, the next disclosures that would change the picture are a financing agreement, a construction start and evidence of how quickly output can rise once production begins.

Until then, Alabama has secured the location. The $1.8 billion is the company’s planned investment, and the sources of that money remain undisclosed in the site announcement.

Sources & evidence

Source checked8 sources · 13 figures

Figure receipts

Every figure in this article, with the source it came from.

Niron Magnetics

Dothan site selection announcement

News release · Nov 20, 2026

  • $1.8 billion Dothan planned investment

    USD, planned · As of Nov. 20 announcement

  • 700 Dothan expected jobs

    Jobs, projected · As of Within five years

  • 2028 Expected start of Dothan construction

    Calendar year · As of Project schedule

  • 2029 Expected start of Dothan production

    Calendar year · As of Project schedule

  • 446 acres Westgate Super Site industrial park

    Acres, full site · As of Site selection

  • 1.6 million sq. ft. Proposed Dothan campus

    Square feet, campus · As of Site selection

  • 22 states Locations considered during site selection

    States · As of Site search

Reuters via Euronext

Reuters Dothan capacity and schedule report

Independent reporting · Nov 20, 2026

  • 10,000 metric tons Dothan planned annual capacity

    Metric tons per year · As of Full design capacity

  • Up to 1,500 metric tons Sartell planned annual capacity

    Metric tons per year · As of Full design capacity

  • 2027 Sartell planned opening

    Calendar year · As of Project schedule

Office of the Alabama Governor

October Growing Alabama awards

News release · Oct 30, 2026

  • $3.5 million Dothan Industrial Development Board public-site award

    USD, site work and public infrastructure · As of Oct. 30 awards

Niron Magnetics

Conditional federal loan announcement

News release · Aug 7, 2026

  • Up to $150 million Federal conditional loan commitment for Sartell

    USD, conditional · As of August 2026

Niron Magnetics

Shakopee Mdewakanton Sioux Community loan announcement

News release · Aug 18, 2026

  • $150 million Shakopee Mdewakanton Sioux Community loan for Sartell

    USD, announced loan · As of August 2026

Sources

Sources used for this piece.

  1. Niron Magnetics · 5 documents

  2. Office of the Alabama Governor · 2 documents

  3. Reuters via Euronext

    Reuters Dothan capacity and schedule report

    Independent reporting · 2026-11-20

As of Nov. 21, 2026. Capacity and timing are plans; the November announcement does not disclose Dothan’s financing.

TickerGrove house illustration for trade coverage: a container ship loading beneath a crane

Get the Morning Brief — Weekday Morning Brief · Saturday Weekend Brief · Sunday Week Ahead

Discuss this story. Join TickerGrove on Discord to talk companies, earnings, and markets, or request future coverage.

Disclaimer

TickerGrove is education and journalism only. It is not investment advice, not a broker-dealer, and not a recommendation to buy, sell, or hold any security.

Nothing on this site is a pick or a return promise. Official economic prints and company filings are dated observations. External quote links open a separate service; TickerGrove does not host those prices.

Companies · All stories