Golar LNG lines up $472 million while a key ship is between contracts
The Hilli’s Cameroon contract ended in July. A refinancing would bring in cash this December, months before the floating LNG plant is due to start work in Argentina.
Golar LNG has signed a refinancing agreement that it expects to bring in about $472 million in December, while one of its floating liquefied natural gas plants is between contracts.
The Hilli finished an eight-year assignment in Cameroon in July and is not due to start its next one, in Argentina, until the second half of 2027.
The timing matters because losing most of a quarter’s earnings from the Hilli already showed up in Golar’s results. The December proceeds would come from extending and expanding an existing sale-and-leaseback, not from producing more LNG. They would give Golar more room to pay for shipyard work and other investments before the Hilli goes back to work.
Golar reported the agreement with its third-quarter results Wednesday. Shares closed at $40.50, down 3.4% from Tuesday’s $41.94. That shows how the stock traded on results day, not which part of the update drove the move.
One month of Cameroon earnings instead of three
The Hilli finished its Cameroon contract on July 27 after loading its 156th cargo there. The vessel left in August and reached a Singapore shipyard in September.
A floating liquefaction plant cools gas for shipment aboard LNG carriers. The Hilli can be moved to a new customer when a contract ends, but that does not mean it can keep earning through the move.
Third-quarter revenue fell 32% from a year earlier to $83.73 million. Adjusted EBITDA fell 33% to $55.81 million, and net income attributable to Golar fell 28% to $22.62 million.
The drop was steeper from the immediately preceding quarter: the company said adjusted EBITDA fell about $72 million, mainly because the Hilli contributed for only one month rather than a full quarter. Lower commodity-linked earnings from the vessel also mattered. The Gimi, another floating plant, continued to produce above its contracted volumes, but that did not make up for the loss.
What the refinancing would actually deliver
The amendment with an affiliate of CSSC (Hong Kong) Shipping would increase the Hilli facility to as much as $960 million, extend its maturity to 2038 and lower the financing margin. The $472 million is Golar’s expected net proceeds at closing, not the face value of the facility.
The partners intend to increase the facility further to as much as $1.2 billion. That would make up to another $240 million available, but it needs further approvals and Golar expects those additional draws in 2027 and early 2028. It is not part of the December inflow.
Golar’s presentation puts available liquidity at $2.27 billion. That figure combines $711 million in company-defined cash at September 30, including restricted cash, with $487 million in net bond proceeds received in October, a $600 million undrawn credit line secured by another vessel, and the expected $472 million from the Hilli.
Those pieces add up, but only the first was cash measured at quarter-end.
What has to happen before Argentina pays
Golar had spent $110 million by September 30 against a $350 million budget for the Hilli’s upgrades, relocation and interim costs. That leaves about $240 million of the budget unspent at that date. The comparison shows the scale of the financing relative to the work ahead; Golar has not earmarked the new proceeds solely for the Hilli.
The 20-year deal with Southern Energy in Argentina is expected to contribute $285 million a year in adjusted EBITDA to Golar before commodity-linked upside. That is a company estimate of annual operating earnings on an adjusted basis, not cash flow or earnings Golar expects to collect before operations start.
Southern Energy is still lining up additional buyers for the LNG.
A separate project company, in which Golar owns 10%, has closed $900 million in financing for the pipeline designed to supply the Hilli and a second Golar vessel. The pipeline’s financing is not cash that Golar can spend on its own ships.
A December close is the first test
The refinancing, if it closes in December as planned, would put cash in Golar’s hands well before the Hilli’s new contract starts. It would not bring forward the earnings from Argentina. A later or smaller closing would show up first in the funding plan; a delayed start in Argentina would extend the earnings gap.
The next things to watch are therefore separate: how much cash Golar actually receives, whether the Singapore work stays within budget, and whether the vessel starts earning under the new contract in the second half of 2027. The $2.27 billion liquidity figure does not resolve any of those questions by itself.
Sources & evidence
Source checked3 sources · 21 figures
Figure receipts
Sources
Sources used for this piece.
As of Thursday, Nov. 19, 2026, using Wednesday’s results and regular-session close.

Discuss this story. Join TickerGrove on Discord to talk companies, earnings, and markets, or request future coverage.