Black Hills signs deals to power Google's planned Cheyenne data center with $1.8 billion of new gas generation
The utility expects the contracts, which run through 2048, to add about $150 million of net income in 2030 and says Google will bear the full cost of serving the site. Its shares rose about 4.5% after hours.
Sources
Based on Black Hills' Oct. 6 Form 8-K and news release, its August results release and quarterly report, its June 10 release, cnbc.com market data, and news reports.
Black Hills announced the agreements after U.S. markets closed on Tuesday, Oct. 6, 2026; the new generation and the data center have not been built. The after-hours price is from 7:40 p.m. ET and can change before Wednesday's open. The comparison with 2026 earnings is a TickerGrove calculation from Black Hills' guidance and second-quarter diluted share count.
Black Hills has signed long-term contracts to power a Google data center planned for Cheyenne, Wyo., and will spend $1.8 billion on new natural gas generation to help supply it.
The Rapid City, S.D., utility said after the stock market closed on Tuesday that the agreements took effect Sept. 30 and run through 2048. Neither the power plants nor the data center has been built. Black Hills plans to start delivering energy in late 2027 and expects the site to reach its peak load in 2030.
The project will draw on about 2.7 gigawatts of resources, including reserve margins and excluding added transmission. Black Hills will supply up to 590 megawatts over the grid. Of that, 564 megawatts will come from new gas-fired units it will build between 2027 and 2029 and own through a non-regulated affiliate at its existing Cheyenne Prairie Generating Station, and the other 26 megawatts from market purchases and regular industrial utility service. It will also manage the output of about 2.1 gigawatts of other Wyoming resources under contract to the project, run through a privately managed microgrid, and collect fees for coordinating them. For scale, the company's Cheyenne-area electric utility set an all-time peak of 439 megawatts on July 20.
Black Hills shares rose about 4.5% to $73.95 in after-hours trading as of 7:40 p.m. ET, according to cnbc.com market data, after closing up 0.4% at $70.74 before the announcement.
What Black Hills expects to earn
Black Hills says it will start earning a return on the generation investment when construction begins in 2027, and that the microgrid management fees will begin in late 2027 and rise on a schedule written into the contract. It expects the project to contribute about $150 million of net income in 2030 and about $2.4 billion of unlevered free cash flow through 2048 after the $1.8 billion of construction spending, with the plants fully depreciated by the end of the contract.
That is a big number for a company this size. Its 2026 guidance of $4.25 to $4.45 a share in adjusted earnings, applied to its 76.1 million diluted shares in the second quarter, works out to about $323 million to $339 million for this year, so the 2030 contribution would equal a bit less than half of that, by TickerGrove's calculation. That comparison leaves out the company's pending merger, which would change its size and share count.
It plans to pay for the build with project cash flow, debt and other financing while keeping its investment-grade credit ratings. Google has already advanced $399 million, refundable, to buy equipment with long lead times, and Black Hills expects to pay that back by June 30, 2027.
Who carries the cost
The hard question with data centers is who pays if the load arrives late, shrinks or leaves. Black Hills says the answer here is Google. "Importantly, these agreements and supporting regulatory mechanisms are structured so that Google bears all costs associated with serving the planned data center throughout the life of the project," said Linn Evans, Black Hills' president and chief executive.
The company listed cost pass-through terms, full recovery of the generation investment over the contract so other customers are protected from stranded plants, provisions covering early termination, and collateral behind the data center's commitments. Those are Black Hills' descriptions. It did not publish the contracts or the rates and fees Google will pay.
From unnamed customer to Google
Tuesday's announcement names a customer Black Hills had described for months. The release says Google's advances came under the parties' generation reservation agreement, a bridge deal Black Hills' Wyoming utility signed in April with a prospective customer planning a 1.8-gigawatt data center, so equipment could be reserved while the two sides negotiated. Those advances reached $285 million by June 30, and the parties raised the total to $377 million in July, according to the company's quarterly report. In June, Black Hills said Crusoe was no longer the development partner but that the project had not been paused and was tracking for service in early 2028.
Local reporting filled in the rest. Cowboy State Daily reported in July that county planning filings identify Google as the owner of a 2.7-gigawatt campus 8 miles south of Cheyenne, now called Project Tembo, and that Google's application says Tallgrass Energy will combine power from Black Hills Energy, fuel cells and its own plant. In September, a Google executive told residents that its investments there amount to $17 billion, Cap City News reported. Black Hills did not name the site on Tuesday, and its release included no comment from Google, which on the same day announced a separate long-term deal to buy power from Constellation Energy's nuclear plants.
Permits, power lines and a pending merger
A certificate for the Robinson substation was approved in May and an air quality permit for the Cheyenne Prairie expansion in August, while an industrial siting permit for the expansion was filed in July. Black Hills also expects to need more transmission for this project and other large customers in the region, spending it calls upside to its current capital plan. It has asked Wyoming regulators for a mechanism to bill transmission costs directly to large customers, filed for a South Cheyenne transmission expansion in September and plans another transmission filing in the fourth quarter.
Black Hills is also trying to finish its all-stock merger with NorthWestern Energy, agreed in August 2025, which would rename the combined parent Bright Horizon Energy. Montana's utility regulators are the last approval the companies need. Their decision is due by Oct. 12 but could be extended to Nov. 10, the Daily Montanan reported last month.
A Wyoming utility will build $1.8 billion of gas generation to power a planned Google data center
Black Hills is a utility that sells electricity and natural gas in eight states, including Wyoming. Google plans to build a data center near Cheyenne, and Black Hills has signed contracts through 2048 to supply it with power. Black Hills will spend $1.8 billion building new gas-fired generation and will also manage power from other suppliers for the site. It expects the deal to add about $150 million to its yearly profit by 2030 and says Google, not its other customers, will pay the costs of serving the data center.
Black Hills signs Google Cheyenne contracts through 2048: $1.8 billion for 564 megawatts of gas, 590 megawatts grid service, 2.1 gigawatts managed, about $150 million of 2030 net income
Definitive agreements (a large power contract services agreement and a generation facilities agreement) effective Sept. 30, 2026, terms through 2048. Total resource mix about 2.7 gigawatts including reserve margins, excluding added transmission; service from late 2027, peak load 2030 (June guidance was early 2028). Up to 590 megawatts grid-connected: 564 megawatts nameplate of new gas generation at Cheyenne Prairie Generating Station, owned through a non-regulated affiliate, built 2027 to 2029 for $1.8 billion; 26 megawatts from market purchases and industrial tariff service. About 2.1 gigawatts of third-party Wyoming resources managed through a private microgrid under the large power contract service tariff, earning microgrid management fees on a contracted ramp from late 2027. Return on generation investment from construction start in 2027; about $150 million of net income in 2030; about $2.4 billion of unlevered free cash flow through 2048, net of capital spending; fully depreciated by 2048. Google refundable advances $399 million, to be repaid by June 30, 2027 (was $285 million at June 30 and $377 million after the July amendment). 2026 adjusted earnings guidance $4.25 to $4.45 a share; 76.1 million diluted shares in the second quarter, implying about $323 million to $339 million (TickerGrove calculation). Wyoming electric peak 439 megawatts on July 20. NorthWestern Energy all-stock merger pending Montana approval, decision due by Oct. 12, extendable to Nov. 10. Shares $73.95 after hours, up 4.54% (7:40 p.m. ET), after a $70.74 close.
What is still unknown
Black Hills did not disclose the rates or fees Google will pay, the return it will earn on the new plants, how much debt or stock it will issue, or how much extra transmission spending the project will need. Black Hills' release did not name the campus or say how much power the data center will ultimately use. Black Hills also did not say whether the contracts need further sign-off from Wyoming regulators; its cautionary language lists regulatory and licensing approvals and contract conditions among the risks.
Document trail
Sources & evidence
Sources used for this piece.
Black Hills via SEC (sec.gov)
Company filing · 2026-10-06
Black Hills via SEC (sec.gov)
Black Hills 2026 second-quarter earnings release reaffirming 2026 guidance (Form 8-K, Exhibit 99)
Company filing · 2026-08-05
Black Hills via SEC (sec.gov)
Black Hills current report announcing the Cheyenne data center agreements (Form 8-K, Item 7.01)
Company filing · 2026-10-06
Black Hills via SEC (sec.gov)
Black Hills quarterly report for the period ended June 30, 2026 (Form 10-Q)
Company filing · 2026-08-06
Black Hills via GlobeNewswire (globenewswire.com)
Black Hills Corp. provides an update on 1.8-gigawatt project in Cheyenne
Company press release · 2026-06-10
Cowboy State Daily (cowboystatedaily.com)
Google revealed as the owner behind Wyoming's largest data center project, now Project Tembo
News report · 2026-07-08
Cap City News (capcity.news)
Google, stepping in for Crusoe, pitches 700-acre data center campus to Laramie County
News report · 2026-09-10
Daily Montanan (dailymontanan.com)
Public Service Commission votes to take up merger decision with new member
News report · 2026-09-24
Reuters, carried by krro.com
Black Hills plans $1.8 billion investment to power Google's data center
News report · 2026-10-06
cnbc.com market data
Black Hills regular-session and after-hours quote
Market data · 2026-10-06
Visual brief
Verified figures
Sources & evidenceBlack Hills planned investment in new gas generation, 2027 to 2029
$1.8B
USD
2027-2029
Black Hills via SEC (sec.gov)Black Hills Corp. executes definitive agreements to serve Google's planned data center in Cheyenne, Wyoming (Form 8-K, Exhibit 99.1)Company filing · 10-06-2026MW
up to 590 megawatts
Grid-connected energy service Black Hills will provide
2026-10-06
Black Hills via SEC (sec.gov)Black Hills Corp. executes definitive agreements to serve Google's planned data center in Cheyenne, Wyoming (Form 8-K, Exhibit 99.1)Company filing · 10-06-2026Expected net income from the project in 2030
about $150M
USD
FY2030
Black Hills via SEC (sec.gov)Black Hills Corp. executes definitive agreements to serve Google's planned data center in Cheyenne, Wyoming (Form 8-K, Exhibit 99.1)Company filing · 10-06-2026